The first phase of the renovation works of seven streets of the neighborhood of San Cristobal carried out by the Town Hall and the CARM enters its final stretch (11/04/2017)

The improvements consist of pavement renovation, replacement of services and burial of wiring, and installation of a new supply and sanitation network.

The second phase, consisting of more than thirty streets, will begin after Easter

The Councilor for Works of the City of Lorca, Eulalia Ibarra, and the Director General for Land Planning, Architecture and Housing, Nuria Fuentes, visited this morning the works of seven streets that belong to the first phase of renovation of the neighborhood of San Cristóbal , Which are already at 90 percent execution, and are being carried out by the Ministry of Development and Infrastructures and the Lorca Consistory.

Nuria Fuentes commented that "they are works in Gilberte, Ponce de León, Rio Duero, Contreras, Tizón, Avellaneda and Ferrer streets, which are expected to be finished in early May. Importance as it is a further step in the reconstruction of Lorca, which is a priority and is the result of work, coordination and effort of the Autonomous Community and the City. "

The Director General of Territorial Planning announced that "the works that are part of the second phase of remodeling of the neighborhood of San Cristobal in the streets Rio Miño and Rincón de Oliver have already begun, and in the thirty remaining streets will begin after Easter".

The performances will be carried out in the streets Escalante, Melchor Navarro, River Segre, River Júcar, Sil River, Colmenar, Almanzar, Aragón, Beteta, Tomás Soler, Los Veras, Higuericas, Grajalva, crossing Ródenas, Miguel Ángel, Juan López, Funes, Montijo, Cayetano Lorca Navarro, Berrocal, Calvario Viejo, Tello, Charco, Serón, Río Mundo, García Bolea, Fray Beato, Pedro Soler, Juan Mínguez, Eulogio Periago and Abellaneda.

Eulalia Ibarra explained that "the works consist of the renovation of the paving, replacing it mostly by paving stones, replacement of electricity supply services, supply and sanitation network, construction of a new rainwater collection network, which did not exist, Burial of service cabling and modernization of telecommunications services, and work on improving the accessibility of these vials and energy efficiency with the installation of LED luminaires in public lighting. "

The Councilor for Works has added that "in the arrangement of the second phase of streets will invest 6 million euros, and will use 26,000 square meters of pavement, 1,116 square meters of asphalt, 323 new street lamps with low consumption LED luminaires will be installed , 5,500 linear meters of low voltage piping, 4,800 linear meters of supply lines, 4,400 square meters of sanitation pipelines, 2,220 linear meters of rainwater piping and 6,670 linear meters of telecommunications wiring will be installed.

The actions in these roads are part of a much larger project of comprehensive renovation of the Lorca neighborhood of San Cristóbal, which began in 2007, covers a total of 58 streets and involves an investment by the Community of more than 7, 5 million euros.

The works are financed by the Autonomous Community within the action plan that develops in the city with charge of the European Investment Bank (EIB) loan, and will be executed by the City Council.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información