Portal de Lorca

www.portaldelorca.com

Lorca - SpanishLorca - English
detail of Lorca

 

The Mayor announces the award of the construction works of the new logistics base of Limusa to a Lorca company for almost 2 million euros (17/07/2018)

Together with the integral modernization project of the Waste Management Center of Barranco Hondo, which entails an investment of 2.25 million euros, it constitutes a strategic project that Lorca will benefit from for decades.

The Mayor of Lorca, Fulgencio Gil, has reported that the City Council, through its municipal cleaning company (Limusa), has awarded a Lorca company the construction of its new logistics base.

This is a project that has been working over the last few years with the aim of providing Limusa with modern, versatile facilities close to the urban center, which will allow a faster, more economical and efficient response to the cleaning demands that our municipality presents.

The First Edil has indicated that this work, which was attended by a total of 9 companies, started with a bid base budget estimated at € 2,163,568.95, which has been reduced to € 1,909,350.

The processing of this action, which encompassed technical and economic criteria, contemplates the signature of the contract this month, foreseeing the start of work for this same summer, ending foreseeably throughout the first four months of 2019. It is a strategic project which will be financed entirely with Limusa's own resources.

It will suppose a remarkable saving to the municipal coffers and will count on buildings that will lodge offices, mechanical workshop, center of washing and clothes for personnel.

All the companies that decided to participate in the process were able to present their offers through the Limusa contracting profile, where they had all the information, which was also available on the public sector contracting platform.

This new equipment will allow Lorca to have a much more modern, operational and functional service infrastructure, characteristics that are underlined by their closest location and well connected to the urban center, which allows a capacity to respond to any type of eventuality much faster and more effective, while significantly reducing the effort of moving machinery that is suffered so far.

The new facility for installation of operational base and logistics of Limusa, will have the following buildings and equipment:

- Building for offices administration, meeting room-dining room, changing rooms, workshop, warehouses and laundry vehicles.

- Covered parking for vehicles.

Parking for judicial vehicle deposit.

- Control booth access to the premises.

- Booth pressure groups.

General urbanization of compound composed of:

Previous actions, existing demolitions, etc ...

Consolidation and improvement of the land.

Perimeter retaining walls.

Formation of planters and paving.

Sanitation, Stormwater, Low Voltage, Outdoor Lighting, Video Surveillance, etc.

The reference plot is irregular and slightly flat, with an area of ​​14,045.17 m2, allocated 6,347.22 for installations corresponding to the operational and logistics base and another 4,396.68 m2 for legal vehicle storage.

The Mayor has indicated, in relation to the general aspects of the project, that the urbanization enclosure integrates the buildings to achieve the least visual impact.

More than 1,800 m2 of planters will be located, both in the entire perimeter of the enclosure and in the interior of the plot, with irrigation from the recovery of water from the municipal swimming pools of the Felipe VI complex, the different planters will have a wooded plantation and shrubs (cypresses, oleanders, rosemary, Abelina, Lantana, etc ...) that form a pleasant and quiet environment. We proceed to enable 100 covered parking spaces, through the construction of metal canopies, thus prolonging its useful life.

The area corresponding to the Judicial Deposit of Vehicles will have 4,300 m2 and 199 units for parking.

The water derived from the obligatory renovation of the municipal swimming pools of the Felipe VI Sports Complex will be reused.

To this end, a network has been designed to channel the excess water to the site, which will be reused for irrigation of gardening, laundry and refueling of washing machines, among other issues.

The new logistic base of Limusa will be equipped with a lighting of high energy efficiency by installing more than 100 LED spotlights for the general lighting of the enclosure and its buildings.

With regard to security, the entire enclosure will be closed by metal fencing, establishing a roundabout and pedestrian access control.

28 video surveillance cameras will be installed, forming a wide surveillance belt both inside and outside the buildings. The ship that will house the offices, workshop and laundry room has been equipped with high energy efficiency, projecting an energy building almost null or with high energy efficiency, decreasing the energy demand of its rooms by means of highly efficient solutions in its thermal envelope (façade, floors, roof and voids).

The building incorporates more than 70% of solar thermal energy for production of sanitary hot water and photovoltaic installation.

The workshop and laundry area has been equipped with the most sophisticated machinery for the repair, maintenance and conservation of the company's vehicles.

It has also included the complete equipment for the use of offices, toilets and clothing, composed of all the furniture necessary for it, such as desks, work tables, lockers, banks ...

Prior to the start of the works are going to perform previous actions such as demolitions and earthworks, foundations, provision of rainwater and sanitation network, outdoor lighting, paving, locksmith, painting, gardening and irrigation, as well as signage.

The total constructed area amounts to 1,412.07 m2, covering 2 floors.

Its distribution includes on the ground floor building for offices administration, meeting room, dining room, changing rooms, workshop, warehouses and laundry vehicles.

The upper floor, on the other hand, includes a warehouse for various uses.

These constructions foresee areas for offices, clothing, workshop and laundry.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información