IU Lorca denounces that the works of Alameda de Cervantes do not include the planned underground containers (01/10/2018)

The councilor of this training, Gloria Martin, lamented that despite the investment of 3.2 million euros, the City Council does not take advantage to promote accessibility and modernize infrastructure in this way

The councilor of Izquierda Unida-Verdes, Gloria Martín, has denounced a new deficiency in the regeneration works of the Alameda de Cervantes.

On this occasion, it has warned of the placement of garbage containers on the surface in areas where they were planned to be buried, which is prevented by the normal transit of pedestrians.

"People with reduced mobility who need a wheelchair or those who go with baby carts, will have to use the road because the containers occupy practically the entire sidewalk," he explained .. In that sense, the mayor of IU-Greens lamented that, despite the costly investment made in this way, the City Council does not take advantage to promote accessibility and modernize infrastructures.

Martin recalled that the work will have a cost of 3.2 million euros and had to be completed last July, so he complained again about the slowness of the work attributed to the lack of workers hired by the company concessionaire

"The delay is increasing the damage caused to neighbors and merchants, despite all the warnings we have made in this regard," he said.

As if that were not enough, "the local government team of the PP sold neighbors idyllic images that have little to do with the final result," said Martin.

"Neither enough parking spaces nor underground containers and we'll see how the rest are," he warned.

This is not to mention that the Railway Infrastructure Administrator (ADIF), under the Ministry of Public Works, has halted the regeneration works in the zone of the level crossing and in part of the Camino Marín, "as long as the informative study of the urban integration of adaptation of the high performance of the railway network "as it passes through the city.

The mayor of IU-Greens demanded that the works comply "scrupulously" with the technical specifications agreed upon because otherwise "it would be a scam".

He also asked for the placement of underground containers "as planned."

"It's a pity that now they have to be building new pavements and patching, but we can not let the promised to the neighbors not be fulfilled," he concluded.

Source: IU-verdes Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información