Portal de Lorca

www.portaldelorca.com

Lorca - SpanishLorca - English
detail of Lorca

 

Green light for the demolition of the electrical substation in La Viña, whose removal will last 2 months (20/04/2011)

The Town Planning stresses that "is the latest step in meeting a demand that excites us all, say goodbye to the substation of the Vineyard."

The budget for the demolition work is over 165,000 euros.

Councilman Urban Area of ​​the Municipality of Lorca, Francisco Garcia, has been reported that the city council has granted permission to demolish for the electrical substation in La Viña, a construction that, as secure from Iberdrola, last 2 months.

The license covering refers to the dismantling of the electrical substation in La Viña, and the demolition of civil works, structures, buildings, drainage and sanitation and infrastructure that supports it.

The Town Planning stressed that "we are talking about a work of great interest to the municipality, especially for residents of the slums of San Antonio and La Viña. With this work will gain in power quality, since it is done in the new substation with all the guarantees and security of the substation, modern, fully covered and isolated. The adjacent neighbors improve their quality of life, since they will throw and cables that cross the streets near their homes. They also promote an improvement in the aesthetic conditions by removing the mesh wiring. The city also will win this important area of ​​over 25,000 m2, which once developed will provide important green spaces and public facilities that will serve for the enjoyment of all residents. We ultimately, closer to enforce a claim that excites us all, say goodbye to the substation of the Vineyard. "

Francisco Garcia has indicated that the license is granted once the new substation, called "The Horse" is almost finished with an implementation rate of over 75%.

The substation now be dismantled is located on the old road to Granada, occupying a plot of 24,675 m2, of which they are engaged in building plant to 960, and has a built below ground surface of 820 m2.

The existing substation has two outdoor parks, one of 132 and a 66 KV.

Their distribution is made, apart from a number of free spaces without question, a network infrastructure that integrates electrical substation and a control building and maintenance of these facilities.

There is also a detached house, currently unused and a series of secondary electrical infrastructure.

Building to be demolished has a length close to 25 years.

The project includes the following works:

Cancellation of the rush of facilities services.

Disconnection and removal of existing switchgear.

Demolition of buildings within the plot.

Excavation to remove underground tanks.

Withdrawal of gardening in an urbanized area.

The total budget for the dismantling and demolition contracts amounting to a total of 165,372 euros.

The period that provides Iberdrola in all these operations is approximately two months.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información