Guevara Palace of Lorca can be visited at Easter after restoration for the damage caused by earthquakes (29/01/2013)

The Department of Culture explained that this year will be visits to buildings without furniture so it can be seen in full detail the actions performed on this baroque building.

The Department of Culture of the City of Lorca, Sandra Martinez, reported that during Holy Week you can visit the Palacio de Guevara, after completion of rehabilitation works are being finalized for the damage caused by the May 11 earthquake .

Martinez explained that "to facilitate Lorca and visitors can observe in detail the action taken on the building and its essential features, we have decided that during the year 2013 are made visits to this example of baroque furniture that prevented without fully enjoy executed in restoring the building. This building is an attraction in itself, so now we have the opportunity to enjoy it as we had never before seen, and nothing we hide her beauty. Already in 2014 the furniture back. "

The mayor has indicated that jobs are at 85% of its execution, as there have been several studies of the finish of the rooms and the porch under the tutelage of the Directorate General of Cultural Assets of the Autonomous Community.

Specifically, the work had been completed consolidation and restoration to lack of cleaning and consolidation of the main facade and little details and touches.

In addition, the restoration of the facade of courtyard is finished to final treatment failure, which can not be given until all jobs are completed patio.

Furthermore, in the box has been restored staircase dome, which has already been cleaned and illuminated, while the ladder has been sewn, removing the struts and ending the cleanup and restoration of stairs and masonry.

Moreover, the restoration work of the yellow room murals are almost completed, and locksmith work, lacking the final treatment of the front door.

Similarly, in the rooms of the main floor finishes are taking to the walls and then place soil.

Also, running intervention in carpentry, for example the patio door is fixed.

Also are finalizing lighting and power installations, such as the lighting of the upper arches is finished and tested.

The work is being executed by a Joint Venture Company in which a company integrates lorquina and involve an investment of € 587,521.49 from the 1% Cultural Development Ministry, while the service works address, address the implementation and coordination of safety and health of the consolidation works of the Palace of Guevara was also awarded to a team of architects Lorca amounting to € 23,682, but the cost was borne by the Consistory Lorca.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información