Councilman Agriculture oversees the work that the Ministry of Environment runs in the districts of listening and Almendricos to repair roads affected by flooding (18/02/2013)

These crossings Nogalte the boardwalk with the Camino de Vera and the Rambla de Almendricos with the way the transfer.

It is improving road safety by constructing speed bumps, the recalzado of the walls and the resurfacing of the pavement.

Councilman Works and Municipal Services City of Lorca, Angel Mecca, made a visit this morning to oversee the upgrading works being carried to term by the Government of Spain, through the General Directorate of Rural Development and Forest Policy of the Ministry of Agriculture, Food and Environment, in different channels and our municipal roads.

Mecca has moved to the hamlet of listening, particularly to the area where the boardwalk Nogalte converge with the path of Vera.

Mecca has explained that this is a requested action by the city council because of the damage caused by the flooding of last September, causing severe damage to watercourses, and secondary roads ramblizos communication of several councils.

These tasks, which also cover works along the natural course of the Rambla de Nogalte, have a budget amounting to 580,000 euros.

The mayor of Agriculture said that "we are talking about jobs we request the Government of Spain after the floods last year and whose response has been quick and effective. Indeed we must remember that this enclave was declared immediate area of ​​operation processing to perform emergency repairs of damage to different infrastructures, which determined last November. Processing was equally rapid, since in December approving the budget cited by the Department of Rural Development and Forestry Policy for these actions. "

Mecca Ruzafa explained that the actions that are being contemplated lorquino territory basically two works:

Performance at the convergence of the Rambla de Nogalte with Vera Road, in the hamlet of listening.

In this section the flood badly damaged the road being reopened to traffic once temporarily eliminate with major conditions.

The consequences of the condition of the flood were breaking the road at crossings with Nogalte boardwalk.

Works at the crossroads of the transfer with Almendricos boardwalk, in the same parish.

The situation is the same as above, seriously affecting road and asphalt.

In both cases the work will be focused at restoring security and communications traffic through the construction of road humps and recalzado of retaining walls.

It is anticipated that the works are completed in approximately 45 days if no consideration incidents arising in the development thereof.

Angel Mecca has indicated that the execution of the work has been entrusted to the Public Utility Agrarian Transformation (Group Tragsa), while the direction of the same is being addressed by the technical staff of the Ministry.

Work began in January in the area between the road and crossing Almendricos the boardwalk Nogalte the Camino de Vera.

Source: Ayuntamiento de Lorca

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información