The Ministry of Development, Public Works and Planning awarded before the end of April the repair and pavement strengthening of the RM-621 road Lorca Puri, affected by the earthquakes of 2011, in the section between 2.9 and 4.6 kilometers, to restore the optimal traffic conditions and regain the conditions of its tread.
The Minister of Development, Francisco Barnabas, said that "this pathway is formed by a straight line along the entire stretch" with lane width varies between 3.20 and 3.50 meters without shoulders.
He added, "has a multitude of hits on neighboring farms intensive agricultural use, and following earthquakes suffered damage and were cracking and breaking of the firm and margins".
Bernabe said that, for these reasons, "has decided to act to remedy the structural deficiencies of firm precarious state of the roadside and poor drainage conditions, also intervening in accordance with the conditions of accessibility available along the path. "
The actions have a budget of 241,777 euros tender and a deadline of two months.
The work, which will begin in May, be the repair and sanitizing of torches;
extension of a wearing course of five centimeters, after adhesion layer;
the replacement of nozzles steps salvacunetas access to adjoining properties;
and replacement of the marking.
Source: CARM